Development:: Temple Extension Phase- 1

Temple Extension Phase- 1 is one of the biggest development at Nathdwara.
Special Suit Rooms - Donation Scheme
<i>Temple Extension Phase - I (Day View)</i> <i>Temple Extension Phase - I (Night View)</i> <i>Temple Extension Phase - I (Night View)</i> <i>Temple Extension Phase - I (Night View)</i> <i>Temple Extension Phase - I (Night View)</i> <i>Temple Extension Phase - I (Cottage View)</i> <i>Temple Extension Phase - I (Cottage View)</i> <i>Temple Extension Phase - I (Cottage View)</i> <i>Temple Extension Phase - I (Cottage View)</i> <i>Temple Extension Phase - I (Cottage View)</i> <i>Temple Extension Phase - I (Cottage View)</i>
TitleDescription
Total Project Cost Rs51.00 Crores
Proposed Construction Area 225000 sq.ft.
Facilities proposed 1) Exhibition Hall
2) Waiting Hall
3) Restaurants
4) Waiting Space for 25000 persons
5) Clock Room
6) Lockers
7) Public Utility Services
8) Temple Board Offices
9) 28 Donor Cottages
Date of Start of work 07-09-2005
Present Status of work 1) Civil works has been completed.
2) Finishing under progress.
Time schedule of completion of the project. Finishing work (G.Floor) & Podium: July 2010
Entire project: March 2013
Expenditure incurred upto 31-01-2013 Rs34.51 Crores